Case story with refinery maintenance planning
Critical emergency shutdown valves
- Totally 23 ESD valves were analyzed based on the diagnostics
- All were taken into maintenance workshop and
- 14 were ok as shown by diagnostics
- 9 valves were maintained fully
- As a result customer achieved following benefits
- Maintenance costs reduced by 58%
- Maintenance shutdown time was kept on schedule